LOT 1 Construction of Peja 3 Substation 400/110kV and Associated Transmission System Works Installation Works
Investor/End user: KOSTT (Transmission system and market operator)
Year of completion: 2010-2011
Building of 400kV switchyard with double busbar system :
- Two 400kV bays
- One 400kV busbar measuring bay
- One 400kV coupling bay
- One Transformer Bay
Building of 110kV switchyard with double busbar system :
- Five 110kV bays
- Pne 110kV busbar measuring bay
- Pne 110kV coupling bay
- Pne 110kV Transformer Bay
Installation of power Transformer 400/115/10.5kV,300/300/1MVA:
- Assistance during installation and commissioning
- Primary and secondary connections
- Cabling and earthing connection
Implementation of installation works in secondary side :
- Control and protection: installation of panels, cabling, assistance during commissioning
- AC&DC implementation works: installation of panels, cabling, assistance during commissioning
- Electrical installation of control building and relay houses: lighting, sockets, fire alarm.
- Outdoor lighting;
Others:
- Realization of earthing system, lightning protection and measurement
- False floor control building and for relay house
PROJECT Ref.: Improvement of Transmission Network- Sector Programme IV and V – LOT 1 PO9503830981- Extension of SS Peja 3 with two new feeders 400 kV and 110kV for Transformer 2 400/110kV
Investor/End user: KOSTT (Transmission system and market operator)
Year of completion: 2016-2017
Building of one 400kV Transformer bay :
- Erection of steel structure
- Erection of 400kV primary equipment
- Commissioning of 400kV primary equipment
- Extension of 400kV double busbar
- Primary connections
Building of one 110kV Transformer bay:
- Erection of steel structure
- Erection of 110kV primary equipment
- Commissioning of 110kV primary equipment
- Primary connections
Building of one 110kV OHL bay:
- Erection of steel structure
- Erection of 110kV primary equipment
- Commissioning of 110kV primary equipment
- Primary connections;
- Extension of 110kV double busbar
Works in installation of power Transformer 400/115/10.5kV,300/300/1MVA
- Primary and secondary connections
- Cabling and earthing connection
Implementation of installation works in secondary side :
- Control and protection: installation of panels, cabling, assistance during commissioning
Civil works :
- Design for civil works: foundations, cable channels
- Building of foundations for primary equipment for new feeders
- Extension of cable channels
- Realization of earthing system for new feeders, lightning protection and measurement.